Qeexid/Sharaxaad

  • It takes three years to finish this project.
  • the first-year total budget is 69,168,000.
  • 57,168,000 is Beneficiarys (Salary) while remained 12 million birrs is budget 

la keeni-karo

The Productive Safety Net Programme (PSNP)

Faahfaahin

  • Aagga Hirgelinta:

    All-City Asphalt 

  • Ka faa'iidaystayaasha:

    All Jigjiga Community

  • Xafiis: Urban greenery, Beatification, Sanitation and Environmental protection Agency
  • Duration: May 02 2024 - May 02 2024
  • Miisaaniyad: 69,168,000 Birr